The first few days of a screed are counter-intuitive. You shouldn't try to dry it quickly; you should try to prevent it from drying too fast. This is called curing, and it is what determines most subsequent defects.
Until the setting process is complete, the cement needs its water to finish its chemical reaction. If the surface loses this water too quickly, it shrinks more than the mass underneath, resulting in a network of fine cracks.
In practical terms, during the first two to three days:
Only then should you gradually open up for ventilation to begin the actual drying process.
A hardened screed is not a finished floor. Subsequent trades are the second leading cause of damage: dropped tools, scaffolding feet, debris left on the floor, or stacks of tiles or boards placed in the same spot.
A heavy point load on a young screed creates a puncture mark that will only become visible once the flooring is installed. If work must continue, you should roll out protective panels or boards in traffic areas and distribute material stockpiles.
Leaving a plastic film stuck to an anhydrite screed for too long can cause stains and delay drying. Sweeping a young screed with water to clean it is another bad idea. Finally, walking on it too soon leaves permanent footprints: see when you can walk on a fresh screed. For the rest, the list of mistakes to avoid before pouring a screed usefully completes this overview.