How long between sprayed PUR and the screed?

Sprayed PUR sets in under 24 hours. The screed can follow as soon as the foam is sanded level and covered with a membrane, often within a few days depending on the site schedule.

Sprayed PUR has a scheduling advantage: unlike a screed, it does not require a long drying time. The interval between the two depends primarily on the intermediate steps.

‍

Foam hardening

The foam expands in a few seconds and hardens in less than 24 hours, as indicated on our page thermal insulation. During this time, avoid walking on it to prevent crushing. The spraying process is described in the data sheet sprayed PUR.

‍

Sanding, then the film

Once sprayed, the foam forms a slightly uneven surface. It is sanded down to the required height to provide a level base, which is essential for a screed of uniform thickness. A separation film is then laid before pouring, to ensure the cement paste does not stick to the insulation.

‍

What really determines the timeline

Once these steps are complete, there is no need to wait any longer. The actual timeline depends on the schedule: availability of the screeding team, potential installation of underfloor heating pipes, and approval of the levels. The full process is in our article on installing a screed.

Most recent questions

During the works
Insulation
Underfloor heating

Can underfloor heating be laid directly on the insulation?

Yes, that is the rule: the pipes are fixed on the insulation layer, then embedded in the screed. The insulation must be flat, resist compression and be covered with a membrane.

Before the works
Insulation
Renovation

Should you insulate an upper floor above a heated room?

Thermally, hardly: heat does not leak between two heated rooms. Upstairs, acoustic insulation against impact noise is what matters, except above an unheated space.

Before the works
Insulation

Is sprayed PUR affected by moisture in the base?

Once in place, closed-cell PUR absorbs little water. But it must be sprayed onto a dry base, and it does not replace treating moisture rising from the ground.

Before the works
Insulation
Renovation

How do you measure the height available to insulate a floor?

Start from the finished floor level set by thresholds and adjoining rooms, measure down to the highest point of the slab, then subtract the floor finish and the screed: what is left is the space for insulation.