How do you know a screed is really dry?

Only a carbide bomb test counts, on a sample taken through the full depth. A screed that feels dry can still be very wet at its core.

This is the most expensive question to answer by eye. A screed that looks light, hard, and dry to the touch can still contain a lot of water three centimeters deep. Installing flooring over this screed means trapping that water under an airtight barrier.

‍

The only measurement that counts

The reference method is the calcium carbide meter, also known as the CM test. A sample is taken with a chisel through the entire thickness, crushed, and then reacted with calcium carbide in a pressure vessel. The resulting pressure indicates the actual moisture content of the mass.

The thresholds commonly required before installing flooring are as follows:

  • Cement screed : 2% CM maximum, and 1.5% if it is a heated screed.
  • Anhydrite screed : 0.5% CM maximum, and 0.3% if it is a heated screed.

The difference between the two types is significant and often surprising: an anhydrite screed must be significantly drier than a cement screed before receiving flooring. The specifications of the flooring and mortar manufacturer always take precedence over these values.

‍

Indicative methods and their limitations

A pin-type or capacitive moisture meter provides an immediate reading, but it only measures the first few millimeters. It is useful for comparing different areas, not for deciding whether to proceed with installation.

The plastic film test remains useful as a free preliminary check: a square of polyethylene taped down hermetically for 24 to 48 hours. If condensation appears underneath, there is no need to go any further; the screed is not ready.

‍

Do not confuse timeframes with measurements

The rule of one week per centimeter up to four or five centimeters, and much slower thereafter, provides a rough idea for project planning. It never replaces a measurement, as drying also depends on ventilation, the season, and the type of mortar.

Our article drying the screed before tiling or parquet flooring details the timeframes for each type of flooring. And if the schedule is tight, first look at what is reasonable to do to speed up drying.

Most recent questions

During the works
Insulation
Underfloor heating

Can underfloor heating be laid directly on the insulation?

Yes, that is the rule: the pipes are fixed on the insulation layer, then embedded in the screed. The insulation must be flat, resist compression and be covered with a membrane.

Before the works
Insulation
Renovation

Should you insulate an upper floor above a heated room?

Thermally, hardly: heat does not leak between two heated rooms. Upstairs, acoustic insulation against impact noise is what matters, except above an unheated space.

During the works
Insulation

How long between sprayed PUR and the screed?

Sprayed PUR sets in under 24 hours. The screed can follow as soon as the foam is sanded level and covered with a membrane, often within a few days depending on the site schedule.

Before the works
Insulation

Is sprayed PUR affected by moisture in the base?

Once in place, closed-cell PUR absorbs little water. But it must be sprayed onto a dry base, and it does not replace treating moisture rising from the ground.

Need a reliable partner for solid screeds, or thermal or acoustic insulation?

Contact us
Arrow right icon