The output of a screed project can vary tenfold depending on the technique used. This figure often dictates the overall renovation schedule, as all subsequent trades depend on it.
The figures above assume an accessible and clear site. In practice, four factors cause them to plummet: pumping distance, floor level, subdivision into small rooms, and the thickness to be poured.
An 80 m² apartment on the third floor divided into six rooms will take longer than a 200 m² open-plan ground floor. Each doorway requires a stop, and each room requires its own leveling. A site that is well-prepared, cleared, and marked out before the arrival of the screed contractor can easily save half a day.
Regardless of the output, a surface area delimited by joints must be poured in one go, without interruption. Resuming in the middle of a room creates a line of weakness that will crack sooner or later. It is therefore better to divide the project into logical zones and accept an extra day than to stop in the wrong place.
This is also why you need to plan the layout of the home during the pour: our fact sheet do you need to move out while a screed is being laid detail the practical consequences.